General Industry Cooperation (GIC)

Project description
The object includes a billet storage, a furnace, mill and cooling bed areas as well as a final product store for producing rebar.
Requirements
Continuous ventilation of the a.m. production areas to provide acceptable room conditions for the staff and the process related machinery. In this project smoke ventilation has been combined with Natural Ventilation.
Solution
AEROVENT Middle East W.L.L. implemented the principle of Natural Ventilation in combination with smoke ventilation. Ridge and slope ventilators Type AEROTOP-I were selected as air exhaust components. They are equipped with electric driven volume dampers which can be closed if required. Air inlet louvres Type AEROFLOW-JR-D were selected as air inlet components. They are operated electrically, the following positions can be adjusted "open"-45 deg"-"closed". The optimum aeration of the building has been achieved with the a.m. system components. In addition, the requirements of smoke ventilation designed according to DIN Standard have been fulfilled.
Project duration
AEROVENT Middle East W.L.L. was involved in the early project phase. The fabrication, the supply and the co-ordination of the erection work were performed according to the general project time schedule.
Specialities
Due to the close and constructive co-operation with the plant designer, the general contractor and the client it was possible to take all necessary project and basic data into consideration and to integrate it in the general project time schedule.